Facilities under construction



Facilities under construction

 

Work on the new propellant storage area (ZSE), located in the previous propellant service area, was completed and it was handed over to ESA in mid-November.

The new storage area was chosen because it was close to the future Vega launch site and because the earlier facilities had become obsolete and were unnecessarily over-sized. CNES took every precaution to protect the environment during its development: 

 ·         Detection and safety resources were optimized by grouping various storage facilities together (for launcher propellant, satellite propellant, fuel and oxidants),

 ·         Spillage catchment basins were installed to avoid products from leaking into the ground,

 ·         A propellant drainage system, constructed of compartmentalized gutters, was created in order to retrieve toxic products and to limit environmental impact in the event of leakage,

 ·         Effluent collection and handling practices during nominal operations were adapted to liquefy gaseous effluents before handling. This is done by means of a washing column, etc.

 The Ground Sub-Directorate of the CNES Launch Vehicle Directorate supervised the ZSE construction project. CNES awarded the fluids and light current contract to Cegelec Space and the civil engineering contract to Nofrayane.